American Legion Bridge and I-270 Multimodal Corridor

What the project is, why it is needed, and how Maryland will decide how to deliver it.

The project

Evaluating Delivery Approach

MDOT and MDTA are actively assessing the viability of delivering the project through a public private partnership (P3). This page explains what the project is, why it is needed, how that decision gets made, and the steps that would follow if a P3 is determined to be the best delivery option for the State. No decision has been made. Each step depends on available funding and future decisions.

What the Project Is

This is a generational project that is needed to improve the economic and physical mobility of the most congested corridor in Maryland. It will replace the 60+ year old American Legion Bridge, add high occupancy toll lanes, and add new paths, bike lanes, and sidewalks.

$6.5 billion

in expected economic activity

3,000 + jobs

expected to be created

60+ years

since the American Legion Bridge opened
in 1962

Additional Benefits

Improves safety

  • Full shoulders on the bridge and its approaches for disabled and emergency vehicles

  • Fewer crashes on the 1-270 West Spur and the ramps in Maryland and Virginia

  • A barrier separated bike and pedestrian path across the bridge

Addresses system preservation and state of good repair

  • Replaces the American Legion Bridge, repaired in 1986, 2008, 2009, and 2021

  • Replaces 16 existing bridges and more than 650,000 square feet of aging bridge deck

Improves multimodal mobility and freight movement

  • Nearly 20% more vehicles across the American Legion Bridge

  • Less delay for freight and on local roads

  • 3 miles of new shared use path, including a new crossing of the Potomac River

Provides investment in transit services for Montgomery County

  • Funding to support priority Montgomery County transit improvements

  • Toll free access to the new lanes for transit vehicles

How Maryland will Decide MDOT SHA logo

MDOT and MDTA are actively assessing the viability of delivering the project through a public private partnership (P3).  This is how that decision gets made, and what follows if a P3 is found to be the best option for the State.  No decision has been made.

STAGE 1

Agency Screening

Listen and evaluate

PIM released

November 2026

Current Step

Industry one on one meetings

December 2026

Secretary and Maryland Transportation Authority (MDTA) Board approval of P3 concept

Q1 2027

Presolicitation Report

Q2 2027

STAGE 2

P3 designation

Review of the agency recommendation

Presolicitation Report review

Q2 2027

Board of Public Works agenda

Q3 2027

PUBLIC VOTE

Board of Public Works vote

Q3 2027

STAGE 3

Solicitation and agreement

A competitive process to select a partner and enter a project agreement

Solicitation process

Q3 2027 to Q3 2028

Review of P3 agreement

Q4 2028

PUBLIC VOTE

Board of Public Works vote

Q4 2028

Execution

2029

What happens at each step

STAGE 1

Agency Screening

Listen and evaluate

PIM released

November 2026

Current Step

The Presolicitation Information Memorandum is released by MDOT SHA and MDTA.

Industry one on one meetings

January 2027

MDOT SHA and MDTA meet with builders, investors, and operators to hear their perspectives.

Secretary and MDTA Board approval of P3 concept

Q1 2027

After information is gathered from industry, approval will be sought from the MDOT Secretary and the MDTA Board to further advance a P3 concept and develop a Presolicitation Report.

Presolicitation Report

Q2 2027

If the agencies decide to recommend a P3, the Presolicitation Report is approved.

STAGE 2

P3 designation

Review of the agency recommendation

Presolicitation Report review

Q2 2027

The report is submitted for review to the required committees in the General Assembly, the Comptroller, and the Treasurer, and posted online for the public.

Board of Public Works agenda

Q3 2027

After evaluating any comments, the P3 designation request is placed on the Board of Public Works agenda.

PUBLIC VOTE

Board of Public Works vote

Q3 2027

The Board of Public Works votes on whether to designate the project as a P3.

STAGE 3

Solicitation and agreement

A competitive process to select a partner and enter a project agreement

Solicitation process

Q3 2027 to Q3 2028

A public advertisement is issued, highly qualified teams are shortlisted, a request for proposals is issued, and a recommended partner is selected.

Review of P3 agreement

Q4 2028

The agreement is submitted for review to the required committees in the General Assembly, the Comptroller, and the Treasurer, and posted online for the public.

PUBLIC VOTE

Board of Public Works vote

Q4 2028

The Board of Public Works votes on whether to approve the P3 agreement.

Execution

2029

The agreement is executed, the partner secures its financing, and construction follows starting in 2029.

Timing is anticipated and may change.  Each step depends on available funding and future decisions.  Both Board of Public Works votes take place in public meetings.

Key Terms

Presolicitation Information Memorandum (PIM)

A document that describes the project and the delivery options under consideration, and invites industry feedback before any decision.

Presolicitation Report

The business case for a P3 if selected as the preferred delivery model by MDOT and MDTA. It explains why a P3 should be pursued, including an analysis of the value difference between public and private delivery options. It is sent to the required committees in the General Assembly, the Comptroller, and the Treasurer and posted online for the public.

Public private partnership (P3)

A long term agreement in which a private partner designs, builds, finances, operates, and maintains a public facility, with appropriate risk allocation between the State and the partner. The State keeps ownership.

Board of Public Works

Maryland's Governor, Comptroller, and Treasurer. The Board approves P3 designations and P3 agreement in public meetings.

Record of Decision

The federal approval, issued in August 2022, that completed the environmental review of the I-495 and I-270 Managed Lanes Study.